What is the correct synchronization job schedule for completing this task?

You wish to synchronize data from transaction SU24 in the SAP S/4HANA production system into SAP Access Control for use in building a rule set.

What is the correct synchronization job schedule for completing this task?
A . It is not possible to synchronize SU24 data from a production system
B . Repository Object Sync followed by an Action Usage Sync
C . Action Usage Sync followed by Role Usage Sync
D . Authorization Sync

Answer: D