What is the sensitivity of the project to changes in material costs?

CORRECT TEXT

A project has an NPV of £1,200,000. The present value of material costs which are included in the NPV calculation are £8,000,000.

What is the sensitivity of the project to changes in material costs? Give your answer to the nearest whole percentage.

Answer: 15%