Users have been experiencing slow network response times, and management has asked the network technician to provide evidence of network improvement. After optimizing the network, which of the following would be required?
Users have been experiencing slow network response times, and management has asked the network technician to provide evidence of network improvement. After optimizing the network, which of the following would be required?
A . IDF/MDF documentation
B . Change management
C . Performance baseline
D . Physical diagram
Answer: C