During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
A . When the Product Owner identifies new work.
B . As soon as possible after they are identified.
C . When the Scrum Master has time to enter them.
D . During the Daily Scrum after the Development Team approves them.

Answer: B