What do you have to consider for the two lists at this stage?

A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists.

What do you have to consider for the two lists at this stage? (Choose two)
A . The stock/requirements list was updated the moment it was accessed.
B . The MRP list displays the production order.
C . The MRP list has the status "processed".
D . The stock/requirements list displays the production order.

Answer: A,D

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments