What do you do during Sprint Execution? Please choose the correct answer.

What do you do during Sprint Execution? Please choose the correct answer.
A . End a sprint when the sprint backlog items are all complete
B . Measure the sprint progress with a percentage complete report
C . Hold a retrospective at the end of each week
D . Present status of selected user stories in the sprint scope on a scrumboard

Answer: B