Who determines the tasks that are required to complete the committed backlog items in a sprint? Please choose the correct answer.
Who determines the tasks that are required to complete the committed backlog items in a sprint? Please choose the correct answer.
A . Project Manager
B . Product Owner
C . Project Team
D . SCRUM Master
Answer: C