In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal? Please choose the correct answer.
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal? Please choose the correct answer.
A . Prepare
B . Explore
C . Realize
D . Deploy
Answer: D