When a change request is received, the business analyst is responsible for:
When a change request is received, the business analyst is responsible for:
A . analyzing the impact on business and underlying systems.
B . ensuring that change-related incidents are minimized in production.
C . prioritizing and scheduling the changes requested.
D . analyzing the impact to the project schedule and budget.
Answer: A