What requirements prioritization technique should be used to determine which requirements will be delivered?

A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window.

What requirements prioritization technique should be used to determine which requirements will be delivered?
A . Multivoting
B . Time-boxing
C . Budget analysis
D . MoSCoW

Answer: D