Which method would best minimize requirements risk?
A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs.
Which method would best minimize requirements risk?
A . Stakeholder analysis
B . Questionnaires
C . Group decision making
D . Prototyping
Answer: B