Where should this information be captured?
During a project steering committee meeting, the project manager reports that a formerly supportive key ream member has become resistant to and negative about changes.
Where should this information be captured?
A . Responsible, accountable, consult, and inform (RACI) matrix
B . Stakeholders engagement assessment matrix
C . Risk register and issue log
D . Work performance reports
Answer: B