What document should the project manager use to ensure that payment delay information is documented for this project?

A company has a longstanding client who is often late with payment. The company now has a new project with this client.

What document should the project manager use to ensure that payment delay information is documented for this project?
A . Risk management plan
B . Historical information and lessons learned repository
C . Assumption log
D . Project charter

Answer: C