A project manager suggests training a software development team on unit testing techniques that can be applied during the coding phase. In addition, the project manager recommends the procurement of a server to run test cases during software development.
Of what is this an example?
A . Quality management budget
B . Appraisal costs
C . Prevention costs
D . Software testing budget
Answer: B