What should the project manager do?

Prior to the implementation of a system upgrade, a team member discovers a critical detect in the current system mat must be fixed.

What should the project manager do?
A . Take no further actions since the project scope has been finalized.
B . Implement the fix and install it with the upgrade.
C . Notify the operational manager, as this is not a project issue.
D . Notify the project sponsor and execute the Perform Integrated Change Control process.

Answer: D