What should the project manager have consulted to avoid this?
During project execution, several concerned stakeholders confront the project manager with concerns. The project manager discovers that these stakeholders’ expectation^ were unrecorded and hence unmet
What should the project manager have consulted to avoid this?
A . Stakeholder analysis
B . Project charter
C . Stakeholder engagement plan
D . Communications management plan
Answer: A