What should the project manager do next?

During planning, a project learn documented the possibility that new hardware could arrive up to 45 days late and delay the project’s delivery date One month into the project the manufacturer notifies the project manager that the hardware will be shipped 20 days sooner than anticipated

What should the project manager do next?
A . Adjust the procurement statement of work (SOW).
B . Issue a change request
C . Update the risk register.
D . Modify the budget

Answer: C

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments