In what category should this new risk be included?
A project manager develops a risk breakdown structure (RBS) and divides it into four categories Later, the team identities a regulation issue with one of the customer’s requirements.
In what category should this new risk be included?
A . External
B . Technical
C . Organizational
D . Project management
Answer: A