What tool or technique is the team using?

A performance report indicates a variation in a product’s specifications. The project manager calls an emergency meeting during which all team members offer suggestions for the possible cause of the variance.

What tool or technique is the team using?
A . Cause-and-effect diagram
B . Scatter diagram
C . Matrix diagram
D . Root cause analysis (RCA)

Answer: D