What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project management project? NOTE: There are 3 correct answers to this question.

What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project management project? NOTE: There are 3 correct answers to this question.
A . Accounting integration for this project is active
B . The project type must allow time recording with the CATS
C . The role type must allow time recording with CATS
D . The planned efforts is on the task

Answer: A,B