Which parts you add afterwards directly in PS?

You are in portfolio management and create a project system (PS) project from an item.

Which parts you add afterwards directly in PS? NOTE: There are 3 correct answers to this question
A . Network activities
B . PS texts
C . Documents
D . Network components
E . WBS elements

Answer: A,B,C