Given this information, which of the following is the SLE?
An organization is looking to build its second head ofce in another city. which has a history of ooding with an average of two oods every ‘I00 years. The estimated building cost is $1 million. and the estimated damage due to flooding is half of the buildings cost.
Given this information, which of the following is the SLE?
A . $50,000
B . $200000
C . $500,000
D . $1.000000
Answer: C