What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
A . Project Management Information System
B . Integrated Change Control
C . Configuration Management System
D . Scope Verification
Answer: C
Explanation:
The change management system is comprised of several components that guide the change request through the process. When a change request is made that will affect the project scope. The Configuration Management System evaluates the change request and documents the features and functions of the change on the project scope.