Which of the following requirements did the testing plan confirm?

The outputs of the old and new applications were compared side by side.

Which of the following requirements did the testing plan confirm? (Select two.)
A . High availability
B . Performance
C . Connectivity
D . Data integrity
E . Sizing
F . Security

Answer: B,D