When an Agile project team receives an “emergency request” during an iteration, which is the best first step that the Agile project manager should take?

When an Agile project team receives an “emergency request” during an iteration, which is the best first step that the Agile project manager should take?
A . Stop work on unfinished user stories and work on the urgent request.
B . Call a team meeting and change the iteration scope to include the request.
C . Provide the customer with options provided by the project team.
D . Explain that the team cannot do the added work until the next iteration.

Answer: C