At the start of a project we are told to “walk the process” from beginning to the end. We do this to_____________________.

At the start of a project we are told to “walk the process” from beginning to the end. We do this to_____________________.
A . Meet the workers
B . Draft a Process Map
C . See what inventory is involved
D . Check the repair stations

Answer: B