Stakeholders are only allowed to meet with the Scrum Team at Sprint Review.

Stakeholders are only allowed to meet with the Scrum Team at Sprint Review.
A . True
B . False

Answer: B

Explanation:

Getting feedback from Stakeholders is a crucial activity in Scrum. Working with stakeholders frequently ensures the team to focus on the right things to build. Although it is required to have Stakeholders at Sprint Review, they can also engage with the Scrum Team during Product Backlog Refinement, Sprint Planning or during the Sprint if the Scrum Team requires it.