Scrum is based on which of the following?

Scrum is based on which of the following?
A . Defined process.
B . Complex process.
C . Empiricism.
D . Hybrid model

Answer: C

Explanation:

Scrum addresses complex problems in complex environments and asserts that knowledge comes from experience and making decisions based on what is known.

What is known can only be discovered in hindsight.