While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must consider which of the following as inputs?

While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must consider which of the following as inputs?
A . Length of Sprint, Agreed Actionable Improvements, Done Criteria, Team Calendar.
B . Assigned Action Items, Business Improvements, Dependencies, Team Calendar.
C . Length of Sprint, Previous Sprint Velocity, Dependencies, Team Calendar.
D . Proof of Concept, Previous Sprint Velocity, Done Criteria, Team Calendar.

Answer: C

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments