What is the shortest number of days in which the project can be completed?
Refer to the exhibit.
The figure below shows the network diagram for the activities of a large project.
What is the shortest number of days in which the project can be completed?
A . 21 days.
B . 22 days.
C . 27 days.
D . 51 days.
Answer: C