When is it most appropriate for a Development Team to change the definition of “Done”?

When is it most appropriate for a Development Team to change the definition of “Done”?
A . During Spring Planning.
B . Prior to starting a new Sprint.
C . During the Sprint Retrospective.
D . Prior to starting a new project.

Answer: C