Which two things should the Development Team do during the first Sprint? (Choose two.)

Which two things should the Development Team do during the first Sprint? (Choose two.)
A . Make up a plan for the rest of the project.
B . Analyze, describe, and document the requirements for the subsequent Sprints.
C . Develop at least one piece of functionality.
D . Analyze, design, and describe the complete architecture and infrastructure.
E . Create an increment of potentially releasable software.

Answer: C,E