Which option is correct when using Virtual Switching System?

Which option is correct when using Virtual Switching System?
A . Both control planes forward traffic simultaneously
B . Only the active switch forward traffic
C . Both data planes forward traffic simultaneously
D . Only the active switch handle the control plane

Answer: C