What should the Scrum Master do?

Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams.

What should the Scrum Master do?
A . Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint.
B . Teach them that it is their responsibility to work with the other teams to create an integrated increment.
C . Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.
D . Visit the five teams each day to inspect that their Sprint Backlogs are aligned.

Answer: C

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
4 Comments
Inline Feedbacks
View all comments
M
M
4 years ago

Correct answer is B.

bla
bla
4 years ago

B Should be the answer

PK
PK
5 years ago

Agree !!
I found others questions here and the answer is not correct !

mikel
mikel
5 years ago

Answer C cannot be correct. The Scrum Master should teach the developers that it is their responsability to work together with other Teams to make suer that they create an integrated increment. I cannot imagina that crating a consolidated plan for the entire Sprint should be a Task to be performed by the Scrum Master. Development Teams organise their own work during the sprint. The Scrum Master is to Coach them on how to accomplish that.