What happens if the opportunity is edited before July 23 and no longer meets the criteria?

An opportunity record, created with a close date of July 30, meets the criteria of a time-dependent workflow rule. The time-dependent action is scheduled for July 23.

What happens if the opportunity is edited before July 23 and no longer meets the criteria?
A . The time-dependent action is automatically removed from the queue.
B . The time-dependent action will execute on July 30.
C . The time-dependent action is put on hold.
D . The time-dependent action will execute on July 23.

Answer: A

Latest DEV-450 Dumps Valid Version with 65 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments