Which resource informs a storage specialist if a Technical and Delivery Assessment (TDA) has to be done?

Which resource informs a storage specialist if a Technical and Delivery Assessment (TDA) has to be done?
A . IBM Pre-sale TDA Checklist
B . Systems Assurance Product Review Guide
C . Trigger Criteria and Designated Product List
D . Digital Techline Center

Answer: A

Explanation:

The  Technical Delivery Assessment (TDA) pre-installation checklist and worksheets document

provides several worksheets that the customer must complete for eachXIV

system. Use the worksheets to record information that is needed by the IBM

installation planning representative (IPR) andIBM service representativeto

install and configure theXIV system.

https://www.ibm.com/support/knowledgecenter/en/STJTAG/com.ibm.help.xivgen3.doc/Gen3/PG/xiv_pln3overview.html