When would the next backup run, if all prior backups completed successfully?
Refer to the exhibit.
A backup policy uses a Full Backup schedule with a schedule type of Frequency: 1 days. The start window for the schedule is configured as shown in the exhibit:
The administrator runs a manual backup at 10:00 on Thursday.
When would the next backup run, if all prior backups completed successfully?
A . Friday at 2:00
B . Friday at 10:00
C . Monday at 2:00
D . Monday at 10:00
Answer: B