What should you do?
You manage a project schedule by using Project Professional 2013.You are concerned about project costs.After viewing the Cost Variance column, you realize that the project has a cost variance of $5,000.00.
You need to view graphically which tasks and resources are causing the $5,000.00 cost variance.
What should you do?
A . View the Task Cost Overview report.
B . View the Over Budget Tasks report.
C . View the Resource Graph’s Cumulative Cost view.
D . View the Cost Overrun report.
Answer: D
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments