You are a project manager who uses Project Standard 2013.You are creating a preliminary project schedule and are estimating the number of resources required prior to finalizing the schedule.You do not have named resources to complete the tasks, but you know the resource roles that are necessary.One of the roles needed is architect.You need to estimate how many architect hours are required to complete the work.What should you do?
You are a project manager who uses Project Standard 2013.You are creating a preliminary project schedule and are estimating the number of resources required prior to finalizing the schedule.You do not have named resources to complete the tasks, but you know the resource roles that are necessary.One of the roles needed is architect.You need to estimate how many architect hours are required to complete the work.What should you do?
A . Add a Budget Resource named architect.
B . Add a Work Resource named architect.
C . Add a Material Resource named architect.
D . Add a Cost Resource named architect.
Answer: B
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments