What should you do?

You manage a project for an organization that relies heavily on schedule baselines in Project Standard 2013.A change is approved for an in-progress project which you manage.You enter the new tasks necessary to include the changes to the project schedule.You need to update the baseline in the most efficient manner.

What should you do?
A . Update the current baseline to the baseline1 fields.
B . Copy the current schedule to the baseline fields.
C . Select a range of tasks and update the baseline for the selected tasks.
D . Select a range of tasks and update the schedule to the baseline1 fields for the selected tasks.

Answer: C