Which of the following options is the correct sequence of the four phases of the Information Security Management System (ISMS)?
Which of the following options is the correct sequence of the four phases of the Information Security Management System (ISMS)?
A . Plan->Check->Do->Action
B . Check->Plan->Do->Action
C . Plan->Do->Check->Action
D . Plan->Check->Action->Do
Answer: C