Which job type goes active next?
A NetBackup Master Server has commenced writing four long-running duplication jobs to an AdvancedDisk disk pool. The value of Maximum concurrent jobs for the storage unit and Limit I/O streams for the disk pool are both set to 4.
There are 35 jobs queued on the Master Server that require this disk pool:
– 5 replication jobs with priority 9999
– 10 backup jobs with priority 999
– 20 duplication jobs with priority 99
Two restore jobs that require this disk pool are then submitted with default priority.
Which job type goes active next?
A . Backup
B . Duplication
C . Replication
D . Restore
Answer: D