Which of the following tools will the project manager MOST likely use?

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity.

Which of the following tools will the project manager MOST likely use?
A . Issue log
B . Defect log
C . Change log
D . Task board

Answer: B

Explanation:

During the stabilization phase of recently deployed software, the project manager will most likely use a defect log to track and manage reported bugs. A defect log is a document that contains information about the defects or issues identified during testing or after the deployment of software. It includes the severity of the defect, the steps to reproduce the problem, and the actions taken to resolve the defect.

Reference: CompTIA Project+ Study Guide Section 4.1.

The project manager will most likely use a defect log during the stabilization phase for recently deployed software to record a bug that is compromising data integrity. A defect log is a tool that tracks and documents any errors or flaws found in a software product or system during testing or operation. It usually includes information such as defect ID, description, severity, priority, status, resolution, and responsible person. A defect log can help to monitor and manage the quality of the software product or system and ensure that all defects are identified and resolved before delivery or release.