Which of the following documents would the project manager need in order to find this information?

During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer.

Which of the following documents would the project manager need in order to find this information?
A . SLA
B . TOR
C . SOW
D . NDA

Answer: C

Explanation:

In order to find the client billing rate for a particular engineer, the project manager would need to refer to the SOW (Statement of Work). The SOW is a document that outlines the work to be performed, the timeframe for completion, and the cost of the project. It also includes information about the resources involved in the project and their billing rates.

Reference: CompTIA Project+ Study Guide Section 2.2.

The project manager would need a statement of work (SOW) to find information about the client billing rate for a particular engineer. A SOW is a document that defines the scope of work for a project or contract. It usually includes information such as deliverables, milestones, timeline, costs, payment terms, quality standards, and acceptance criteria. A SOW can help to specify what services or products will be provided by whom, when, where, how, and for how much.