What should you do?

A company produces pipe at certain fixed lengths.

The company must be able to schedule cutting machines. You set up the cutting machines as resources. All cutting resources can produce many of the products. There are some products that cutting machines that can produce longer lengths of product. Only some of the machines can do this.

You need to configure the resources to account for these different products.

What should you do?
A . Build capability related to length and assign to the appropriate resources.
B . Configure the Data/Hour option on the Capacity unit eld on the resource.
C . Create a resource for each length.
D . Create a resource group for each length.

Answer: A