Which sourcing approach would be the most appropriate?

A local council requires facilities management services for ten schools based in their region. This service is a high-spend, high-risk, critical contract.

Which sourcing approach would be the most appropriate?
A . Request for quotation
B . Competitive tendering
C . Statement of source requirements
D . Direct negotiation

Answer: B

Explanation:

Competitive tendering is the most suitable approach for high-risk, high-value contracts as it ensures transparency, fairness, and the selection of the most capable supplier based on predefined criteria.