Which of the following statements regarding the BCMS implementation project and operations is correct?

Which of the following statements regarding the BCMS implementation project and operations is correct?
A . Projects are focused on sustaining the organization, whereas operations focus on retaining or adding value or capability.
B . Projects are ongoing, whereas operations are temporary.
C . Projects are temporary, whereas operations are ongoing.

Answer: C