Before confirming an anticipated completion date with the customer, it is MOST important to
Before confirming an anticipated completion date with the customer, it is MOST important to
A . double check the floor finishes.
B . ensure the date is not a holiday.
C . ensure no components are backordered.
D . create the system maintenance schedule.
Answer: C
Explanation:
Before confirming an anticipated completion date, it is critical to ensure that all components required for the project are available and not backordered. Backordered components can cause significant delays, impacting the overall project timeline. By verifying the availability of all necessary components, you can provide a realistic and reliable completion date to the customer. This step is essential for effective project planning and avoiding unexpected delays.