Which life cycle would be most suitable?
You are the project manager on a construction project for a client in the defence sector. The client has strict regulatory requirements and expects a high level of control and governance throughout the project.
Which life cycle would be most suitable?
A . Iterative
B . Hybrid
C . Incremental
D . Linear
Answer: D
Explanation:
The Linear (or Waterfall) lifecycle is the most suitable for projects that require high levels of governance, control, and strict adherence to regulatory requirements.
Applicability: Linear project management focuses on predefined stages (e.g., requirements, design, implementation) that align with regulatory needs.
Advantages: It allows detailed documentation, structured review processes, and adherence to pre-approved plans, ensuring compliance with defence sector standards.
Alternative Options: Iterative and incremental approaches are less appropriate due to the less structured nature of deliverable evolution in these methods.