Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
A . Estimating remaining durations of activities.
B . The correct recording of actual start dates.
C . Making "downstream" logic revisions as required.
D . Entering the time impacts of delays and change orders.
Answer: A